Chapter 23.94
WIRELESS COMMUNICATIONS FACILITIES

Sections:

23.94.010    Purpose and intent.

23.94.020    Definitions.

23.94.030    Permit requirements by zoning district.

23.94.035    Small cell wireless communications facilities.

23.94.040    Exemptions.

23.94.050    Development standards.

23.94.060    Operation and maintenance standards.

23.94.070    Removal provisions.

23.94.080    Transfer of operation.

23.94.090    Effects of development.

23.94.010 Purpose and intent.

The purpose of this chapter is to regulate the installation of antennas and other wireless communications facilities consistent with Federal law. The City acknowledges the community benefit associated with the provision of wireless communication service and potential public benefit from leasing of publicly owned properties. It is also recognized that unrestricted installations are contrary to the City’s efforts to promote safety and aesthetic considerations. It is not the intent of this chapter to unreasonably limit the reception or transmission of signals or to add excessive permit costs. Rather, it is the intent of this chapter to permit antennas and wireless communications facilities where they can be installed without creating adverse safety and aesthetic impacts on abutting and nearby properties and the overall community. [Ord. 19-2019 §3 (Exh. B), eff. 10-11-2019; Ord. 8-2011 §39(A), eff. 6-24-2011]

23.94.020 Definitions.

Terms unique to this chapter are listed in EGMC Chapter 23.100 (General Definitions). [Ord. 19-2019 §3 (Exh. B), eff. 10-11-2019; Ord. 8-2011 §39(B), eff. 6-24-2011]

23.94.030 Permit requirements by zoning district.

A. Permit Requirements.

1. New Facilities. In an attempt to protect scenic, historic, natural, or cultural resources of the City; to assure land use compatibility with properties adjacent to such facilities; to minimize negative visual, noise and aesthetic impacts; and to protect the general safety, welfare, and quality of life of the community, unless exempt from permit requirements pursuant to EGMC Section 23.94.040, Exemptions, and except as set forth herein or at EGMC Section 23.94.035, Small cell wireless communications facilities, all new wireless communications facilities shall be subject to the permit requirements for the underlying zoning district as provided in EGMC Table 23.27-1 (Allowed Uses and Required Entitlements for Base Zoning Districts). The procedures for any required conditional use permit or minor conditional use permit are provided in EGMC Section 23.16.070, Conditional use permit and minor conditional use permit.

2. Modification to Existing Facility (Including Co-location). Except for eligible facilities requests, modifications and proposed co-locations to an existing wireless facility require an amendment to or issuance of a new conditional use permit or minor conditions use permit, if such a permit was approved prior to the development of the existing wireless facility. Applications qualify for an eligible facilities request if all the following findings can be made:

a. The modification does not increase the height of the existing facility tower by more than ten (10%) percent or twenty (20' 0") feet, whichever is greater;

b. The modification does not propose any equipment that extends from the current limits of the facility tower by more than twenty (20' 0") feet;

c. The modification does not propose more than one (1) new equipment cabinet;

d. The modification will not entail any excavation or deployment greater than thirty (30' 0") feet outside the current site area;

e. The modification will not defeat any concealment elements of the existing tower; and

f. The modification will not violate any prior conditions of approval; provided, however, that the collocation need not comply with any prior condition of approval that is inconsistent with the thresholds for a substantial change.

B. Permit Processing. Permits shall be processed in accordance with the applicable provisions of Division II of this title.

C. Conditions. The designated approving authority may impose conditions on wireless communications facility permits to ensure compliance with all provisions and purposes of this chapter.

D. Findings for Approval. The approving authority may approve or conditionally approve a conditional use permit or minor conditional use permit for a wireless communications facility, where such permit is required, only upon making the following written findings, in addition to the required findings for conditional use permits as provided in EGMC Section 23.16.070, Conditional use permit and minor conditional use permit, based on substantial evidence in the record.

1. All of the following findings are required for the approval of a conditional use permit for any wireless communications facility:

a. The establishment or expansion of the facility demonstrates a reasonable attempt by the applicant to minimize stand-alone facilities.

b. All applicable development standards in EGMC Section 23.94.050 have been met; or, if the application includes a request for an exception to those standards, then the approving body finds that lack of compliance with the development standards would not create adverse visual, noise, or aesthetic impacts to adjacent property.

2. Findings for the establishment of a wireless communications facility that is not co-located with other existing or proposed facilities or a new freestanding pole or tower (at least one (1) finding required):

a. Co-location is not reasonably feasible;

b. Co-location would have greater adverse effects on views, noise or aesthetics as compared with a stand-alone installation; or

c. Co-location is not permitted by the property owner.

E. Findings for Denial. Findings to deny any permit for a wireless communications facility as regulated herein shall be done in writing and supported by substantial evidence contained in the written record. Denial shall not be based on the environmental effects of radio frequency emissions that comply with the Federal Communications Commission emission regulations. [Ord. 12-2022 §3 (Exh. A), eff. 6-24-2022; Ord. 19-2019 §3 (Exh. B), eff. 10-11-2019; Ord. 24-2015 §11 (Exh. I), eff. 2-12-2016; Ord. 8-2011 §39(C), eff. 6-24-2011]

23.94.035 Small cell wireless communications facilities.

Any small cell wireless communications facility, as defined in EGMC Section 23.26.050, shall require a permit as required by EGMC Table 23.27-1. To the extent provided by EGMC Table 23.27-1, a small cell wireless communications facility use shall be a permitted use if such use is consistent with an agreement between the applicant and the City, approved by the Elk Grove City Council, and such installation and operation of the small cell wireless communications facility or facilities are in conformance with the agreement. To the extent there is a conflict between the provisions of the agreement for a small cell wireless communications facility or facilities and this chapter, the terms of the agreement shall prevail. [Ord. 19-2019 §3 (Exh. B), eff. 10-11-2019]

23.94.040 Exemptions.

The following wireless communications facilities are exempt from the requirements of this chapter as specified below and are subject to compliance with other provisions of this title:

A. A wireless communications facility shall be exempt from the provisions of this chapter if and to the extent that a permit issued by the California Public Utilities Commission (CPUC) or the rules and regulations of the Federal Communications Commission (FCC) specifically provide that the antenna is exempt from local regulation.

B. Satellite earth station (SES) antennas which are two (2) meters (6.5616 feet) or less in diameter or in diagonal measurement, located in any nonresidential zoning district. In order to avoid the creation of an attractive public nuisance, reduce accidental tripping hazards and maximize stability of the structure, such antennas shall be placed whenever possible on top of buildings and as far away as possible from the edges of rooftops.

C. Parabolic antennas, direct broadcast satellite (DBS) antennas and multipoint distribution service (MDS) antennas which are one (1) meter (3.2808 feet) or less in diameter or diagonal measurement and Television Broadcast Service (TVBS) antennas, so long as said antennas are located entirely on private property and are not located within the required front yard setback area. This locational requirement is necessary to ensure that such antenna installations do not become attractive nuisances and/or result in accidental tripping hazards if located adjacent to a street or other public right-of-way.

D. Amateur radio antenna structures provide a valuable and essential telecommunication service during periods of natural disasters and other emergency conditions and are therefore exempt from permit provisions of this chapter in compliance with the following standards:

1. Height Limits. In residential zoning districts the height limit is forty-five (45' 0") feet and in nonresidential zoning districts the height limit is sixty (60' 0") feet. However, amateur radio antennas in any district may extend to a maximum height of seventy-five (75' 0") feet; provided, that the tower is equipped with a lowering device (motorized and/or mechanical) capable of lowering the antenna to the maximum permitted height when not in operation.

2. Location Parameters. All antenna structures shall be located outside of required front and street side yard areas. Antenna structures shall also be set back a minimum distance of five (5' 0") feet from interior property lines. If any portion of the antenna overhangs any property line, a design review permit is required to obtain the authorized signature of all affected property owners on the required application form.

3. Tower Safety. All antennas shall be located within an enclosed fenced area or have a minimum five (5' 0") foot high tower shield at the tower base to prevent climbing. All active elements of antennas shall have a minimum vertical clearance of eight (8' 0") feet.

4. Minor modifications (emergency or routine), provided there is little or no change in the visual appearance as determined by the Development Services Director.

E. An emergency standby generator for a macro cell tower site, as defined in Section 65850.75 of the Government Code, shall be exempt from any requirement for a user permit or design review required by this code if it complies with all of the following:

1. The emergency standby generator is rated below fifty (50) horsepower, complies with applicable air quality regulations, has a double-wall storage tank, not to exceed three hundred (300) gallons, and is mounted on a concrete pad.

2. The macro cell tower site at which the emergency standby generator is proposed to be installed is an existing site that was previously permitted by the City.

3. The emergency standby generator complies with all applicable State and local laws and regulations, including building and fire safety codes.

4. The physical dimensions of the emergency standby generator and storage tank are cumulatively no more than two hundred fifty (250 ft3) cubic feet in volume.

5. The emergency standby generator shall be located not more than one hundred (100' 0") feet from the physical structure of the macro cell tower or base station. [Ord. 16-2021 §4 (Exh. B), eff. 9-10-2021; Ord. 19-2019 §3 (Exh. B), eff. 10-11-2019; Ord. 24-2015 §11 (Exh. I), eff. 2-12-2016; Ord. 26-2006 §3, eff. 8-11-2006]

23.94.050 Development standards.

A. General Development Standards. Unless otherwise exempt pursuant to EGMC Section 23.94.040, Exemptions, or as otherwise provided in an agreement approved by the Elk Grove City Council pursuant to EGMC Section 23.94.035, Small cell wireless communications facilities, the following general development standards shall apply to all wireless communications facilities:

1. All wireless communications facilities shall comply with all applicable requirements of the current uniform codes as adopted by the City and shall be consistent with the General Plan and this title, as well as other standards and guidelines adopted by the City.

2. All wireless communications facilities shall be designed, screened and/or camouflaged from the view of surrounding properties and the public view to the greatest extent possible in one (1) or more of the following ways:

a. Co-located with existing facilities or structures so as not to create substantial visual, noise, or aesthetic impacts. To facilitate co-location when deemed appropriate, conditions of approval for conditional use permits shall require all service providers to cooperate in the siting of equipment and antennas to accommodate the maximum number of operators at a given site when found to be feasible and aesthetically desirable;

b. Sited within areas with substantial screening by existing vegetation;

c. Designed to appear as natural features found in the immediate area, such as trees or rocks, so as to be unnoticeable (camouflaged facilities); or

d. Screened with additional trees and other native or adapted vegetation which shall be planted and maintained around the wireless communications facility, in the vicinity of the project site, and along access roads, where such vegetation is appropriate and deemed necessary to screen the facilities. Such landscaping, including irrigation, shall be installed and maintained by the applicant, as long as the permit is in effect.

3. All wireless communications facilities, including on-site generators, shall be designed, located, and operated to have little to no noise impact on the surrounding area or neighborhood, including interference from adverse noise and aesthetic impacts, and at a minimum shall be subject to the City-adopted noise standards contained in EGMC Chapter 6.32 and the General Plan. Failure to comply with the City’s adopted noise standard after written notice and opportunity to cure have been given shall be grounds for the City to conduct a revocation hearing regarding the permit granted pursuant to this section.

4. All permit applications for wireless communications facilities shall include a description of services proposed and documentation certifying applicable licenses or other approvals required by the Federal Communications Commission to provide services proposed in connection with the application.

5. All permit applications for wireless communications facilities shall include a map and narrative description of all telecommunication sites existing, proposed or planned by the applicant in the City and within a one (1) mile radius of the City border. Such applications shall also include an analysis of all reasonable and technically feasible alternative locations and/or facilities (including co-locations) which could provide the proposed communication service.

6. In a residential zoning district, the following development standards shall apply, unless the applicant can demonstrate with substantial evidence satisfactory to the approving authority that such siting limitation will materially inhibit personal wireless service as to a particular small cell wireless communication facility:

a. No small cell wireless communication facility shall be placed within five hundred (500' 0") feet of another small cell wireless communications facility.

b. No small cell wireless communication facility shall be located immediately adjacent to, nor immediately across the street from, a front yard of any residential dwelling.

c. The cumulative total of all associated equipment from all wireless communications providers, including antennas, for a single facility or property shall not exceed twenty-eight (28 ft3) cubic feet in volume.

7. At least ten (10' 0") feet of horizontal clearance shall be maintained between any part of the antenna and any power lines unless the antenna is installed to be an integral part of a utility tower or facility.

8. Development Standards for Antennas (Excluding Amateur Radio Antennas). Unless otherwise exempt pursuant to EGMC Section 23.94.040, Exemptions, the following development standards shall apply to receive-only antennas (ground- and building-mounted), parabolic antennas, and satellite earth stations as defined in this section:

a. Maximum Number. One (1) wireless facility per parcel, unless the applicant can demonstrate the service need for additional antenna.

b. Antenna Location. Parabolic antenna and satellite earth stations shall be ground-mounted in residential zoning districts. In all nonresidential zoning districts, the preference is for building-mounted antennas. No antenna shall be located in the required front or street side yard of any parcel unless entirely screened from pedestrian view of the abutting street rights-of-way (excluding alleys). In all zoning districts, ground-mounted antennas shall be situated as close to the ground as possible to reduce visual impact without compromising their function and all portions of the structure/antenna shall be set back a minimum of five (5' 0") feet from any property line.

c. Height Limit. The height limit for ground-mounted antennas is six (6' 0") feet. However, the height may be increased to a maximum of twelve (12' 0") feet if the setback distance from all property lines is at least equal to the height of the antenna and if the structure is screened in accordance with subsection (A)(8)(d) of this section, Screening. Building-mounted antennas shall not extend above the roofline, parapet wall, or other roof screen or project beyond a maximum of eighteen (18") inches from the face of the building or other support structure.

d. Screening. Ground-mounted antennas shall be screened with a fence, wall or dense landscaping so that the antenna is not visible from the public right-of-way and to minimize the visual impact on abutting properties. Building-mounted antennas shall be screened as follows:

i. Wall-mounted equipment shall be flush-mounted and painted or finished to match the building with concealed cables.

ii. Roof-mounted equipment shall be screened from view of public rights-of-way by locating the antenna below the roofline, parapet wall, or other roof screen and by locating the antenna as far away as physically feasible and aesthetically desirable from the edge of the building.

e. Color. Antennas shall have subdued colors and nonreflective materials which blend with the materials and colors of the surrounding area or building.

B. Development Standards for Amateur Radio Antennas. As part of a minor design review, amateur radio antennas as defined in EGMC Chapter 23.100 may exceed the height limit and/or amend the setback provisions of the exempt amateur radio antenna structures (EGMC Section 23.94.040, Exemptions) only when said regulation will result in unreasonable limitations on, or prevent, reception or transmission of signals. The designated approving authority may issue the design review permit subject to any conditions necessary or appropriate to minimize the safety or aesthetic impacts of antenna installations, provided the conditions do not unreasonably prevent or limit transmission or reception of signals.

C. Development Standards for Towers. The following development standards shall apply to towers (including co-location facilities) as defined in EGMC Section 23.94.020, Definitions:

1. Site Design. All facilities (including related equipment) shall be designed to minimize the visual impact to the greatest extent feasible, considering technological requirements, by means of placement, screening, and camouflage, to be compatible with existing architectural elements, landscape elements, and other site characteristics. The applicant shall use the smallest and least visible antennas possible to accomplish the owner/operator’s coverage objective. A visual impact analysis is required to demonstrate how the proposed facility will appear from public rights-of-way (including public trails).

2. Safety Design. All facilities shall be designed so as to be resistant to and minimize opportunities for unauthorized access, climbing, vandalism, graffiti, and other conditions which would result in hazardous conditions, visual blight, or attractive nuisances.

3. Location. Towers shall not be located in any required front or street side yard in any zoning district. The setback distance from any abutting street right-of-way, residential property line, or public trail shall be equal to the height of the facility (tower and related equipment). Otherwise, the minimum setback distance from all other property lines shall be at least equal to twenty (20%) percent of the height of the tower. Existing towers may be allowed to increase the height without requiring the tower to be relocated as part of the conditional use permit approval, provided the overall maximum height of the tower does not exceed the height limit listed in subsection (C)(4) of this section, unless an exception is approved by the designated approving authority.

4. Height Limit. The height limit for towers shall be as listed in Table 23.94-1 based on the underlying zoning district of the site. Exceptions to the height limit may be granted when the designated approving authority finds that reasonable alternatives do not exist to provide the necessary service. There is no height limit specified for co-locations on existing structures, provided facilities are screened from view of abutting street rights-of-way or camouflaged by matching the color(s) and/or material(s) of the structure to which it is attached.

Table 23.94-1

Height Limit for Wireless Towers 

Zoning District

Height Limit

AG, AR, RD, PR, PS, O, C-O, RMU, VCMU

55 ft.

LC, GC, SC, AC, BP

65 ft.

MP, LI, LI/FX, HI

80 ft.

5. Lighting. Towers and related equipment shall be unlit except as provided below:

a. A manually operated or motion-detector-controlled light above the equipment shed door may be provided, except that the light shall remain off except when personnel are present at night and shall be shielded or directed downward to the greatest extent possible to ensure that light shall not spill over onto abutting properties, especially residential zoning districts or uses; and

b. Tower lighting required by FAA regulation.

6. Landscape. Where appropriate, wireless facilities shall be landscaped so as to maintain and enhance the aesthetic quality of the community and generally screen the ground equipment from public view. The perimeter of the facility, as well as any portion of the leasable area directly adjacent to a public right-of-way, a residential use, or a public trail shall be landscaped with trees, foliage, and shrubs. Trees shall be fast-growing evergreen species, twenty-four (24") inch box in size. Shrubs shall be a minimum fifteen (15) gallon size covering a minimum planter area depth of five (5' 0") feet around the facility. Trees and shrubs shall be planted no further apart on center than the mature diameter of the proposed species.

7. Design/Finish. The tower and related equipment shall have subdued colors and nonreflective materials that blend with the colors and materials of surrounding areas.

8. Advertising. The tower and related equipment shall not bear any signs or advertising devices other than certification, warning or other required seals or signs.

9. Parking. The off-street parking for wireless communications facilities shall be determined by the designated approving authority in conjunction with required development permits. All required parking shall be provided in accordance with EGMC Chapter 23.58, Parking. [Ord. 19-2019 §3 (Exh. B), eff. 10-11-2019; Ord. 31-2014 §3 (Exh. A), eff. 2-13-2015; Ord. 27-2013 §15, eff. 2-7-2014; Ord. 8-2011 §39(D), eff. 6-24-2011]

23.94.060 Operation and maintenance standards.

A. Noise. All wireless communications facilities shall comply with EGMC Chapter 6.32, Noise Control, at all times. Back-up generators shall only be operated during power outages and for testing and maintenance purposes.

B. Nonionizing Electromagnetic Radiation (NIER) Exposure. No wireless communications facility or combination of facilities shall produce, at any time, power densities in any inhabited area that exceed the FCC’s maximum permissible exposure (MPE) limits for electric and magnetic field strength and power density for transmitters. [Ord. 19-2019 §3 (Exh. B), eff. 10-11-2019; Ord. 8-2011 §39(E), eff. 6-24-2011; Ord. 26-2006 §3, eff. 8-11-2006]

23.94.070 Removal provisions.

In the event one (1) or more antennas, towers, or related equipment are not operated for the provision of wireless telecommunication services for a continuous period of three (3) months or more, such antenna, tower, and/or related equipment shall be deemed abandoned. The owner of same shall remove all such items within thirty (30) days following the mailing of written notice that removal is required. If two (2) or more providers of wireless telecommunication services use the antenna support structure or related equipment, the period of nonuse under this section shall be measured from the cessation of operation at the location by all such providers. Failure to remove shall constitute a public nuisance and shall be enforced as such. [Ord. 19-2019 §3 (Exh. B), eff. 10-11-2019; Ord. 26-2006 §3, eff. 8-11-2006]

23.94.080 Transfer of operation.

Any carrier/service provider authorized by the City to operate a specific wireless communications facility may assign the operation of the facility to another carrier licensed by the FCC for that radio frequency; provided, that such transfer is made known to the Development Services Director in writing prior to the transfer and all conditions of approval for the subject installation are carried out by the new carrier/service provider. However, the carrier/service provider may, without written notification, transfer operations of the facility to its general partner or any party controlling, controlled by or under common control with the carrier/service provider. [Ord. 19-2019 §3 (Exh. B), eff. 10-11-2019; Ord. 24-2015 §11 (Exh. I), eff. 2-12-2016; Ord. 26-2006 §3, eff. 8-11-2006]

23.94.090 Effects of development.

The City shall not be liable if development within the City, after installation of the antenna, impairs antenna reception. [Ord. 19-2019 §3 (Exh. B), eff. 10-11-2019; Ord. 26-2006 §3, eff. 8-11-2006]