40.260.260 Zero Lot Line Developments

These developments are allowed in R1-5 and R1-6 districts, or in connection with infill developments. The responsible official shall find that the following conditions exist before any building permit is issued for zero lot line developments:

A.    All zero lot line developments, except land divisions or developments processed pursuant to Section 40.260.110, Residential Infill, are subject to site plan approval.

B.    The side setback on the lot abutting a zero setback lot line shall be at least ten (10) feet.

C.    Notations on the plat and/or covenants running with the land, approved by the Prosecuting Attorney, shall guarantee that required side setbacks of not less than ten (10) feet shall be kept perpetually free of obstructions.

D.    Easements for such purposes as maintenance, or for building projection encroachments beyond a zero setback line, shall be shown on the plat.

(Amended: Ord. 2008-06-02)