6.110A.030 Development inspection fees.

Fees for those development inspection activities contained in Table 6.110A.030 shall be collected prior to inspection:

Table 6.110A.030—Development Inspection Fees 

Section

Activity

Fee

1

 

 

 

Planning Fees

 

 

A

 

 

Wetland1

 

 

 

I

 

 

Request release of performance assurance

79

 

 

II

 

 

Request release of maintenance assurance

103

 

 

III

 

 

Monitoring inspection/permit

 

 

 

 

a

 

First year

600

 

 

 

b

 

Subsequent years

300

 

B

 

 

Habitat

 

 

 

I

 

 

Monitoring inspection/permit

 

 

 

 

a

 

First year

600

 

 

 

b

 

Subsequent years

300

2

 

 

 

Engineering Fees

 

 

A

 

 

Critical Aquifer Recharge Area Permit (CARA) Category I Only

 

 

 

I

 

 

Type 1 site plan inspection

590

 

 

II

 

 

Type 2 site plan inspection

870

 

B

 

 

Drainage Project

 

 

 

 

 

 

Stormwater inspection fee

831

 

C

 

 

Grading Permit – Inspection

 

 

 

I

 

 

100 c.y. or less

254

 

 

II

 

 

over 100 to 10,000 c.y.

862

 

 

III

 

 

over 10,000 c.y.

2,028

 

D

 

 

Grading Permit – Surcharge

 

 

 

I

 

 

Activity lasts 6 to 12 months beyond issuance date

16%

 

 

II

 

 

Activity lasts 12 or more months beyond issuance date

32%

 

 

III

 

 

Activity lasts months beyond permit time, surcharge in A or B above as applicable, plus penalty of

8%

 

 

IV

 

 

Work without permit

Double fee

 

 

V

 

 

Review of engineered grading report

386

 

E

 

 

Inspection – Stormwater and Transportation

 

 

 

 

 

 

Inspection per hour after normal work hours and any reinspection (regardless of time of day)3

Actual salary and benefits for employees performing work plus overhead at a rate of 30%

 

F

 

 

Shoreline Inspection

278

 

G

 

 

Short Plat

 

 

 

I

 

 

Inspection – Stormwater

2,068

 

 

II

 

 

Inspection – Transportation

2,068

 

 

III

 

 

Rural driveways

265

 

H

 

 

Site Plan

 

 

 

 

 

 

Transportation and stormwater

 

 

 

I

a

 

Base fee – Small projects (less than 1.0 acre of impervious surface2)

1,520

 

 

 

b

 

Per sq. ft. fee – Small projects (less than 1.0 acre of impervious surface2)

0.0204

 

 

II

a

 

Base fee – Medium projects (1.0 acre to 4.99 acres of impervious surface2)

3,041

 

 

 

b

 

Per sq. ft. fee – Medium projects (1.0 acre to 4.99 acres of impervious surface2)

0.0100

 

 

III

a

 

Base fee – Large projects (over 5.0 acres of impervious surface2)

6,086

 

 

 

b

 

Per sq. ft. fee – Large projects (over 5.0 acres of impervious surface2) [maximum base fee + per sq. ft. fee $11,000]

0.0039

 

 

IV

 

 

Unoccupied commercial and utility structures – Base fee

507

 

 

V

 

 

Tenant improvements

152

 

 

VI

 

 

Final site plan inspection

507

 

I

 

 

Subdivision (all sizes)

 

 

 

 

 

 

Stormwater

 

 

 

I

 

 

Base fee

1,409

 

 

II

 

 

Per lot fee

140

 

 

 

 

 

Transportation

 

 

 

III

 

 

Base fee

4,440

 

 

IV

 

 

Per lot fee

39

 

J

 

 

System Integrity Review

 

 

 

 

 

 

Maintenance warranty

878

 

 

 

 

 

Stormwater system failure – Engineering review

1,285

Notes:

1    The director may waive a part or all of the wetland permit fees for wetland and buffer enhancements, provided (1) the project is not intended to mitigate for wetland buffer impacts, and (2) the project is not the result of an enforcement action.

2    Impervious surface is defined in Section 40.100.070, Clark County Code.

3    Cost recovery—Contractor will be required to sign an agreement that they will pay actual costs of the inspection. Actual costs will be salary and benefits for employees performing work plus overhead at the rate of thirty percent (30%). The contractor will be sent an itemized billing.

4    For review of projects authorized for overtime, an additional fifty percent (50%) will be added to the permit fees, as applicable.

(Sec. 3 (Exh. A) of Ord. 2001-12-09; amended by Sec. 1 (Exh. A) of Ord. 2002-11-07; amended by Sec. 1 (Exh. A) of Ord. 2004-02-09; amended by Ord. 2004-12-02; amended by Ord. 2005-12-01; amended by Sec. 2 of Ord. 2006-05-27; amended by Sec. 1 of Ord. 2007-04-17; amended by Sec. 1 of Ord. 2007-11-13; amended by Sec. 1 of Ord. 2008-02-01)