The City is authorized to assume the maintenance of stormwater facilities and stormwater treatment and flow control BMPs/facilities approved and constructed following the requirements of Chapter 16.26 IMC after the expiration of the 2-year maintenance period in connection with the subdivision of land if:

A. All of the requirements of Chapter 16.26 IMC have been fully complied with;

B. The facilities, as designed and constructed, conform to the provisions of this chapter;

C. The facilities have been inspected and approved by the Department after their second year of operation;

D. All necessary easements or dedications entitling the City to properly access, operate, and maintain the facilities have been recorded with the King County Recorder’s Office, and a copy has been conveyed to the City;

E. A stormwater facility or stormwater treatment and flow control BMP/facility, which does not meet the criteria of this section, shall remain the responsibility of the applicant required to construct the facility and persons holding title to the property for which the facility was required. (Ord. 2783 § 2 (Exh. A2), 2016; Ord. 2560 § 2 (Exh. A1), 2009; Ord. 2288 § 2, 2000).