Chapter 15.80
EXPEDITED REVIEW OF SMALL RESIDENTIAL ROOFTOP SOLAR ENERGY SYSTEM PERMITS

Sections:

15.80.010    Definitions.

15.80.020    Small residential rooftop solar energy system standard plan and permit application checklist.

15.80.030    Permit application review.

15.80.040    Inspection requirements.

15.80.050    Fees.

15.80.010 Definitions.

A. “Electronic submittal” shall have the same meaning as provided in the Solar Rights Act, Government Code Section 65850.5(j)(2), as the same may be amended from time to time.

B. “Small residential rooftop solar energy system” shall have the same meaning as provided in the Solar Rights Act, Government Code Section 65850.5(j)(3), as the same may be amended from time to time. (Ord. 401 § 3, 2015)

15.80.020 Small residential rooftop solar energy system standard plan and permit application checklist.

A. The city shall adopt standard plan(s) and checklist(s) of all requirements with which small residential rooftop solar energy systems shall comply to be eligible for expedited review. The small residential rooftop solar system standard plan(s) and checklist(s) shall substantially conform to recommendations for expedited permitting, including the checklists and standard plans contained in the most current version of the California Solar Permitting Guidebook adopted by the Governor’s Office of Planning and Research.

B. All documents required for the submission of a small residential rooftop solar energy system permit application, the standard plan(s), and checklist(s) shall be made available on the publicly accessible city website.

C. Electronic permit applications shall be submitted through the method of electronic submittal specified by the building official and shall be available to all small residential rooftop solar energy system permit applicants. An applicant’s electronic signature shall be accepted on all forms, applications, and other documents in lieu of a wet signature. (Ord. 401 § 3, 2015)

15.80.030 Permit application review.

A. An application that satisfies the information requirements in the checklist(s) and standard plan(s) shall be deemed complete.

B. If an application is deemed incomplete, a written correction notice detailing all deficiencies in the application and any additional information or documentation required to be eligible for expedited permit issuance shall be sent to the applicant for resubmission.

C. The building official shall issue a building permit for any complete application that meets the requirements of the approved checklist(s) and standard plan(s) as follows: the same day for over-the-counter applications, within one to three business days for electronic applications, or as soon thereafter as may be practicable. Review of the application shall be limited to the building official’s review of whether the application meets local, state, and federal health and safety requirements.

D. Any condition imposed on an application shall be designed to mitigate the specific, adverse impact upon health and safety at the lowest possible cost. (Ord. 401 § 3, 2015)

15.80.040 Inspection requirements.

A. Inspection requests may be submitted by electronic submittal, as required by the building official.

B. Only one inspection shall be required and performed by the building official for small residential rooftop solar energy systems eligible for expedited review.

C. The inspection shall be done in a timely manner. The building official shall use its best efforts to schedule an inspection within two business days of a request and provide a two-hour inspection window.

D. If a small residential rooftop solar energy system fails inspection, a subsequent inspection is authorized but need not conform to the requirements of this section. (Ord. 401 § 3, 2015)

15.80.050 Fees.

Fees for permits and inspections associated with this chapter may be established by resolution of the city council. (Ord. 401 § 3, 2015)