Chapter 15.25
ELECTRICAL VEHICLE CHARGING STATION REVIEW PROCESS

Sections:

15.25.010    Definitions.

15.25.020    Expedited review process.

15.25.010 Definitions.

(1) The following words and phrases are used in this section are defined as follows:

(a) “Electronic submittal” means the utilization of email, the internet or facsimile.

(b) “Electric vehicle charging station” or “charging station” means any level of electric vehicle supply equipment station that is designed and built in compliance with Article 625 of the California Electrical Code, as it reads on the effective date of this chapter, and delivers electricity from a source outside an electric vehicle into a plug-in electric vehicle.

(c) “Specific, adverse impact” means a significant, quantifiable, direct, and unavoidable impact, based on objective, identified, and written public health or safety standards, policies, or conditions as they existed on the date the application was deemed complete. [Ord. 360 § 1, 2017.]

15.25.020 Expedited review process.1

(1) Consistent with Government Code Section 65850.7, the Building Official shall implement an expedited administrative permit review process for electric vehicle charging stations, and prepare a checklist or submittal guidelines of all requirements with which electric vehicle charging stations shall comply in order to be eligible for expedited review. The City’s checklist/guidelines shall be published on the City’s website.

(2) Consistent with Government Code Section 65850.7, the Building Official shall allow for electronic submittal of permit applications covered by this chapter and associated supporting documentations. In accepting such permit applications, the Building Official shall also accept electronic signatures on all forms, applications, and other documentation in lieu of a wet signature by any applicant.

(3) Consistent with Government Code Section 65850.7, the Building Official shall not condition the approval for any electric vehicle charging station permit on the approval of such a system by an association, as that term is defined by Civil Code Section 4080.

(4) A permit application that satisfies the information requirements in the City’s checklist shall be deemed complete and be promptly processed. Upon confirmation by the Building Official that the permit application and supporting documents meet the requirements of the City checklist, and are consistent with all applicable laws, the Building Official shall, consistent with Government Code Section 65850.7, approve the application and issue all necessary permits. Such approval does not authorize an applicant to energize or utilize the electric vehicle charging station until approval is granted by the City. If the Building Official determines that the permit application is incomplete, he or she shall issue a written correction notice to the applicant, detailing all deficiencies in the application and any additional information required to be eligible for expedited permit issuance.

(5) It is the intent of this chapter to encourage the installation of electric vehicle charging stations by removing obstacles to permitting for charging stations so long as the action does not supersede the Building Official’s authority to address higher priority life-safety situations. If the Building Official makes a finding based on substantial evidence that the electric vehicle charging station could have a specific adverse impact upon the public health or safety, as defined in Government Code 65850.7, the City may require the applicant to apply for a use permit. [Ord. 360 § 1, 2017.]


1

Code reviser’s note: Ord. 360 adds this section as 15.25.010. It has been editorially renumbered to avoid duplication of numbering.