Chapter 15.39
EXPEDITED PERMITTING PROCESS FOR ELECTRIC VEHICLE CHARGING STATIONS

Sections:

15.39.010    Permitting process.

15.39.010 Permitting process.

(a) Permitting. Electric vehicle charging stations which qualify for expedited permit processing, pursuant to Government Code Section 65850.7, shall be subject to the administrative permitting procedures set forth in this chapter.

(b) Expedited Review Process. Consistent with Government Code Section 65850.7, the Building Official shall implement an expedited administrative permit review process for electric vehicle charging stations and adopt a checklist of all requirements with which electric vehicle charging stations shall comply in order to be eligible for expedited review.

(c) Electronic Submittals. Consistent with Government Code Section 65850.7, the Building Official shall allow for electronic submittal of permit applications covered by this chapter and associated supporting documentation. In accepting such permit applications, the Building Official shall also accept electronic signatures on all forms, applications, and other documentation in lieu of a wet signature by any applicant.

(d) Association Approval. Consistent with Government Code Section 65850.7, the Building Official shall not condition the approval for any electric vehicle charging station permit on the approval of such a system by an association, as that term is defined by Civil Code Section 4080.

(e) Permit Application Processing. A permit application that satisfies the information requirements in the City’s adopted checklist shall be deemed complete and be promptly processed. Upon confirmation by the Building Official that the permit application and supporting documents meet the requirements of the City’s adopted checklist, and are consistent with all applicable laws, the Building Official shall, consistent with Government Code Section 65850.7, approve the application and issue all necessary permits. Such approval does not authorize an applicant to energize or utilize the electric vehicle charging station until approval is granted by the City. If the Building Official determines that the permit application is incomplete, he or she shall issue a written correction notice to the applicant, detailing all deficiencies in the application and any additional information required to be eligible for expedited permit issuance.

(f) Technical Review. It is the intent of this chapter to encourage the installation of electric vehicle charging stations by removing obstacles to permitting for charging stations so long as the action does not supersede the Building Official’s authority to address higher priority life-safety situations. If the Building Official makes a finding based on substantial evidence that the electric vehicle charging station could have a specific adverse impact upon the public health or safety, as defined in Government Code Section 65850.7, the City may require the applicant to apply for a use permit.

(g) Appeals. A decision of the Building Official pursuant to this chapter is appealable in writing to the Planning Commission. Such appeal shall be taken by the filing of a notice in writing to that effect with the City Planner within seven calendar days of the Building Official’s decision. (Ord. 2008 § 12, 11-19-19).