(1) The department shall provide notice of application within 10 days after a determination that the application is complete as specified in SCC Table 30.70.050(5). Required notice shall be given in accordance with SCC 30.70.045.

(2) A notice of application posted or published in the official county newspaper or provided by mail on a letter/legal size publication shall include the following information:

(a) Date of application, date of completeness determination, and date of notice of application;

(b) Project description, list of permits requested, assigned county file number, and county contact person;

(c) Any information or studies requested by the department;

(d) Any other required permits not included in the application, to the extent known by the department;

(e) Any existing environmental documents that evaluate the proposed project, including where they can be inspected;

(f) The date, time, place, and type of public hearing, if applicable and if scheduled at the time of the notice;

(g) When notice is for a rezone action or development in a performance standard zone, a statement indicating where the full text and/or map of the rezone action may be inspected;

(h) A statement of when the comment period ends and the right of any person to comment on the application, receive notice of and participate in any hearings, request a copy of the decision once made, and any appeal procedures;

(i) If determined at the time of notice, those development regulations that will be used for project mitigation or to review consistency; and

(j) Any other information determined appropriate by the department.

(3) Mailed notice of application may be provided on a post card.

(4) A post card notice shall contain the following information:

(a) project description;

(b) project file number;

(c) project location;

(d) type of project;

(e) applicable comment dates and notice of where to submit comments;

(f) date the notice of application was published in the official county newspaper;

(g) website address providing access to project information; and

(h) a department contact.

Table 30.70.050(5) Notice of Application Requirements

Application Type

Post

Publish

Mail

Administrative Conditional Use

X

X

X

Binding Site Plan

X

X

X

Building and land disturbing activity permits unless exempt from SEPA as minor new construction under SCC 30.61.035(1)

X

X

X

Code interpretation not related to a specific project

X

Code interpretation related to a specific project

X

X

X

Final Subdivision

[see SCC 30.41A.600 through 30.41A.730]

Flood Hazard Permit - except as provided in SCC 30.43C.020

X

Flood Hazard Variance

X

X

X

Free-standing sign in the RFS zone

X

X

X

SEPA threshold determination and EIS adequacy associated with project permit

X

X

X

Shoreline variance, conditional use, or substantial development permit or permit rescission

X

X

X

Short subdivision and rural cluster short subdivision

X

X

X

Variance

X

X

X

Conditional use and major revision

X

X

X

Preliminary subdivision and rural cluster subdivision, and major revision

X

X

X

Planned Residential Development and major revision

X

X

X

Official site plan or preliminary plan approval in performance standard zones (BP, PCB, IP, GC, T, RB, CRC, RFS, and RI)

X

X

X

Rezone - site specific

X

X

X

Review or revocation of a permit or approval pursuant to SCC 30.71.027

X

X

X

Preapplication Concurrency Decision

X

X

X

Any non-listed Type 1 or Type 2 permit application except Boundary Line Adjustments pursuant to SCC 30.41E.020(1)(c)

X

X

X

(Added by Amended Ord. 02-064, Dec. 9, 2002, Eff date Feb. 1, 2003; Amended by Amended Ord. 05-042, July 6, 2005, Eff date Aug. 8, 2005; Amended by Ord. 06-093, Nov. 8, 2006, Eff date Nov. 26, 2006; Amended by Amended Ord. 07-005, Feb. 21, 2007, Eff date Mar. 4, 2007; Amended by Ord. 08-136, Oct. 29, 2008, Eff date Nov. 24, 2008; Amended by Amended Ord. 10-023, June 9, 2010, Eff date Sept. 30, 2010; Amended by Ord. 20-080, Dec. 16, 2020, Eff date Jan. 9, 2021; Amended by Amended Ord. 22-037, Sept. 28, 2022, Eff date Oct. 9, 2022).